Nicht aus der Schweiz? Besuchen Sie lehmanns.de
The NEC 3 Engineering and Construction Contract - Brian Eggleston

The NEC 3 Engineering and Construction Contract

A Commentary

(Autor)

Buch | Softcover
392 Seiten
2015 | 2nd Edition
John Wiley & Sons Inc (Verlag)
978-1-118-98936-4 (ISBN)
CHF 96,90 inkl. MwSt
zur Neuauflage
  • Titel erscheint in neuer Auflage
  • Artikel merken
Zu diesem Artikel existiert eine Nachauflage
Now Available in Paperback From its launch in 1991 the New Engineering Contract has rapidly overtaken traditional building and civil engineering contracts to become the UK's leading standard form for major construction projects. Additionally, under the generic title NEC 3, there is now a family of New Engineering Contract standard forms.
Now Available in Paperback From its launch in 1991 the New Engineering Contract has rapidly overtaken traditional building and civil engineering contracts to become the UK's leading standard form for major construction projects. Additionally, under the generic title NEC 3, there is now a family of New Engineering Contract standard forms. This book provides a detailed commentary on the latest edition of the main form - NEC 3 Engineering and Construction Contract. It explains how the contract is intended to operate and examines each clause to consider its application and legal interpretation. It draws upon the author's successful book on the second edition of the Engineering and Construction Contract, ECC 2, and it identifies and comments on the changes between ECC 2 and NEC 3. Particular attention is given to the revised compensation event procedures in NEC3, with five chapters of the book devoted to this subject. In-depth analysis is also given to: * The role of the project manager * The obligations of the parties * The liabilities of the parties * The revised dispute resolution procedures

Brian Eggleston, CEng, FICE, FIStructE, FCIArb is a registered arbitrator.

Preface xi Author s note xiii 1 Introduction 1 1.1 Development of NEC contracts 1 1.2 Characteristics of NEC contracts 2 1.3 Structure of the NEC 3 Engineering and Construction Contract 4 1.4 Feedback from ECC 2 5 1.5 Changes from ECC 2 6 1.6 Points of interest in NEC 3 7 2 Main options 11 2.1 Introduction 11 2.2 Contract strategy 12 2.3 Option A priced contract with activity schedule 18 2.4 Option B priced contract with bill of quantities 21 2.5 Target contracts generally 22 2.6 Options C and D target contracts 25 2.7 Option E cost reimbursable contract 26 2.8 Option F management contract 27 2.9 Option W1 dispute resolution 27 2.10 Option W2 dispute resolution 28 3 Secondary option clauses 30 3.1 Introduction 30 3.2 Option X1 price adjustment for inflation 32 3.3 Option X2 changes in the law 32 3.4 Option X3 multiple currencies 33 3.5 Option X4 parent company guarantee 34 3.6 Option X5 sectional completion 35 3.7 Option X6 bonus for early completion 36 3.8 Option X7 delay damages 37 3.9 Option X12 partnering 42 3.10 Option X13 performance bond 44 3.11 Option X14 advanced payment to the contractor 45 3.12 Option X15 limitation of contractor s liability for design 47 3.13 Option X16 retention 48 3.14 Option X17 low performance damages 50 3.15 Option X18 limitation of liability 51 3.16 Option X20 key performance indicators 54 3.17 Option Y(UK)2 Housing Grants, Construction and Regeneration Act 1996 55 3.18 Option Y(UK)3 Contracts (Rights of Third Parties) Act 1999 56 3.19 Option Z1 additional conditions 56 4 Contract documents 58 4.1 Introduction 58 4.2 Entire agreements 59 4.3 Clause 12.4 of NEC 3 60 4.4 Construction of contracts generally 60 4.5 NEC 3 documentation 61 4.6 Essential contract documents 62 4.7 Identified and defined terms 64 4.8 The contract date 64 4.9 Works information 66 4.10 Site information 69 4.11 Contract data 71 4.12 Schedules of cost components 71 4.13 Ambiguities and inconsistencies in the contract documents 74 4.14 Schedule of clauses referring to the works information 75 5 Key players 79 5.1 Introduction 79 5.2 Others 81 5.3 Actions 82 5.4 The employer 85 5.5 Express obligations of the employer 86 5.6 The project manager 87 5.7 Express duties of the project manager 90 5.8 The supervisor 94 5.9 Express duties of the supervisor 95 5.10 Communications 95 5.11 The project manager and the supervisor 100 6 General core clauses 102 6.1 Introduction 102 6.2 Actions 103 6.3 Identified and defined terms 103 6.4 Interpretation and the law 113 6.5 Communications etc. 115 6.6 Instructions 115 6.7 Adding to the working areas 115 6.8 Early warning 116 6.9 Ambiguities and inconsistencies 119 6.10 Illegal and impossible requirements 120 6.11 Prevention 121 7 Obligations and responsibilities of the contractor 126 7.1 Introduction 126 7.2 Design obligations, responsibilities and liabilities 129 7.3 Providing the works 131 7.4 The contractor s design 133 7.5 Using the contractor s design 136 7.6 Design of equipment 136 7.7 People 137 7.8 Working with the employer and others 138 7.9 Subcontracting 140 7.10 Other responsibilities 143 7.11 Express obligations of the contractor 145 7.12 Express prohibitions on the contractor 149 8 Time (and related matters) 151 8.1 Introduction 151 8.2 Starting and completion 154 8.3 Programmes 156 8.4 Revision of programmes 159 8.5 Shortened programmes 161 8.6 Access to and use of the site 162 8.7 Instructions to stop or not to start work 163 8.8 Take-over 165 8.9 Acceleration 167 9 Testing and defects 170 9.1 Introduction 170 9.2 Definitions and certificates 173 9.3 Tests and inspections 177 9.4 Testing and inspection before delivery 179 9.5 Searching and notifying defects 180 9.6 Correcting defects 182 9.7 Accepting defects 184 9.8 Uncorrected defects 185 10 Payments 188 10.1 Introduction 188 10.2 Assessing the amount due 191 10.3 Payments 194 10.4 Defined cost 197 10.5 Payments main option A 197 10.6 Payments main option B 201 10.7 Payments main option C 202 10.8 Payments main option D 207 10.9 Payments main option E 207 10.10 Payments main option F 208 11 NEC 3 compensation event schemes 210 11.1 Introduction 210 11.2 Changes in NEC 3 (from ECC 2) 212 11.3 Outline of procedures 216 11.4 Defining a compensation event 217 11.5 Compensation events as exclusive remedies 217 11.6 Fairness of the compensation event procedures 218 11.7 Unusual features of the compensation event procedures 219 12 Listed compensation events 220 12.1 Introduction 220 12.2 Omissions from the listed events 221 12.3 Works information related events 221 12.4 Employer s default events 224 12.5 Employer s risk events 226 12.6 Project manager/supervisor related events 227 12.7 Physical conditions 231 12.8 Adverse weather 234 12.9 Prevention 235 12.10 Measurement related events 236 12.11 Secondary option clause events 238 13 Notifying compensation events 241 13.1 Introduction 241 13.2 Notifications by the project manager 242 13.3 Notifications by the contractor 244 13.4 Project manager s response to notifications 248 13.5 Last date for notification of compensation events 251 14 Quotations for compensation events 253 14.1 Introduction 253 14.2 Instructions to submit quotations 256 14.3 Instructions for alternative quotations 259 14.4 Submission of quotations 260 14.5 Status of the contractor s quotations 262 15 Assessment of compensation events 265 15.1 Introduction 265 15.2 Changes from ECC 2 266 15.3 General assessment rules 267 15.4 Particular assessment rules 274 15.5 The project manager s assessments 278 15.6 Implementing compensation events 280 15.7 Other financial remedies 281 16 Title 283 16.1 Introduction 283 16.2 Employer s title to equipment, plant and materials 284 16.3 Marking equipment, plant and materials 285 16.4 Removing equipment 285 16.5 Objects and materials within the site 286 17 Risks and insurances 288 17.1 Introduction 288 17.2 Employer s risks 292 17.3 Contractor s risks 295 17.4 Repairs 296 17.5 Indemnity 296 17.6 Insurance cover 296 17.7 Insurance policies 297 17.8 Contractor s failure to insure 298 17.9 Insurance by the employer 298 18 Termination 300 18.1 Introduction 300 18.2 Summary of NEC 3 termination provisions 304 18.3 Termination for any reason 305 18.4 Termination under section 9 306 18.5 Reasons for termination 308 18.6 Procedures on termination 312 18.7 Amounts due on termination 313 19 Dispute resolution 315 19.1 Introduction 315 19.2 Developments in dispute resolution 316 19.3 Meaning of dispute 317 19.4 Adjudication under Option W1 319 19.5 Adjudication under Option W2 329 19.6 Review by the tribunal 333 19.7 The Adjudicator s Contract 336 20 NEC 3 Engineering and Construction Subcontract 337 20.1 Introduction 337 20.2 Core clauses general 339 20.3 Core clauses the subcontractor s main responsibilities 340 20.4 Core clauses time 340 20.5 Core clauses testing and defects 341 20.6 Core clauses payment 341 20.7 Core compensation events 342 20.8 Core clauses title 343 20.9 Core clauses risks and insurance 343 20.10 Core clauses termination 343 20.11 Dispute resolution 344 21 NEC 3 family of contracts 345 21.1 The contracts 345 21.2 NEC 3 Short Contract and Short Subcontract 346 21.3 NEC 3 Term Service Contract 348 21.4 NEC 3 Framework Contract 352 21.5 NEC 3 Professional Services Contract 352 21.6 NEC 3 Adjudicator s Contract 354 21.7 Concluding comment 354 Table of cases 355 Table of clause references 359

Erscheint lt. Verlag 11.5.2015
Verlagsort New York
Sprache englisch
Maße 171 x 247 mm
Gewicht 754 g
Themenwelt Technik Bauwesen
ISBN-10 1-118-98936-8 / 1118989368
ISBN-13 978-1-118-98936-4 / 9781118989364
Zustand Neuware
Haben Sie eine Frage zum Produkt?
Mehr entdecken
aus dem Bereich
Grundlagen und Vorgehensweisen

von Bernd Kochendörfer; Jens H. Liebchen; Markus G. Viering

Buch | Softcover (2021)
Springer Fachmedien Wiesbaden GmbH (Verlag)
CHF 53,15
Bemessung von Stahlbauten nach Eurocode mit zahlreichen Beispielen

von Jörg Laumann; Christian Wolf

Buch | Hardcover (2024)
Springer Vieweg (Verlag)
CHF 83,95